Home Contact Us
Industry Dynamics

Satellite Chemical’s Lianyungang Acrylates Plan and What Buyers Can Verify

See which phase proposes butyl acrylate and acrylic acid capacity in Lianyungang and what approvals and grade evidence buyers need to check.

Published on · Published by MOSINTER GROUP Editorial Team · About 3 min read
Illustration of two overlapping industrial plan sheets with generic tanks and acrylic chips.

Satellite Chemical has proposed a two-phase propylene and downstream materials project at Xuwei New Area in Lianyungang. The proposal lists a butyl acrylate unit in the first phase, with a design capacity of 300,000 tonnes a year. For coatings and acrylic-binder buyers, the filing identifies a potential future source to monitor. It leaves the start-up date, commercial grades and available volumes open.

The cover is an AI-assisted editorial illustration of project planning.

The agreement and the approvals still ahead

Satellite Chemical signed the investment cooperation agreement with the Xuwei New Area administration on 11 November 2026. In its 12 November disclosure, the company put the total planned investment at approximately CNY 20.7 billion, with CNY 12 billion planned for phase one. The board approved the investment proposal. Shareholder review was still required. A separate notice calls an extraordinary shareholders’ meeting on 27 November with the project on the agenda.

The filing also identifies registration, filing, approval and licensing steps whose timing and outcomes remain uncertain. It estimates a construction period of up to three years for phase one without establishing a commissioning date. Buyers can use the shareholder resolution and subsequent project disclosures to check what has actually advanced.

Where the planned acrylates capacity sits

Proposed design capacities in the issuer’s disclosure of 12 November 2026.
UnitPhase one design capacityPhase two additional design capacity
Propane dehydrogenation (PDH)1,000,000 tonnes/year1,000,000 tonnes/year
Acrylic acid300,000 tonnes/year300,000 tonnes/year
Butyl acrylate300,000 tonnes/yearNo additional unit disclosed
Higher alcohols800,000 tonnes/year800,000 tonnes/year

Both phases list acrylic acid units, for a planned combined 600,000 tonnes a year if both are built. The butyl acrylate figure belongs to phase one alone. The issuer says phase two depends on first-phase progress, economics and market conditions. Follow the capacity and status of the relevant unit separately. Pooling figures across units would overstate the project’s potential contribution to butyl acrylate availability.

Which milestone would change a sourcing decision?

At the investment stage, record the issuer, location, unit, phase and next source document in the supply watch. A shareholder resolution can resolve one governance question. Construction or commissioning disclosure can give better evidence about execution. A commercial offer is still needed to identify the actual producing site, grade, specification, lot documentation and terms for the buyer’s destination.

An acrylic-binder buyer can set qualification criteria while a project is still on the watchlist. Confirm the grade specification and test basis, request a representative lot and agree how a trial will be judged in the intended formulation. Plan current orders against qualified offers and applicable shipment conditions. The capacity disclosure supplies no price, delivery commitment or evidence of export availability.

See other coatings industry updates.

Sources